|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00874/16 |
|
|
||
|
|
|
|
|
||
|
|
CEDD Contract No. CV/2012/05 Development of a Bathing Beach at Lung Mei, Tai
Po |
|
|
||
|
|
|
|
|
||
|
|
Monthly
Environmental Monitoring and Audit Report (October 2020) |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Welcome Construction CO., Ltd |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
|
19 February 2021 |
TCS00874/16/600/R0656v2 |
|
|
|
Nicola Hon (Environmental
Consultant) |
T.W. Tam (Environmental
Team Leader) |
|
Version |
Date |
Remarks |
1 |
10 November 2020 |
First Submission |
2 |
19
February 2021 |
Amended
according to IEC¡¦s comment |
executive summary
ES.01 Civil Engineering and Development Department (hereafter referred as ¡§CEDD¡¨) is the
Project Proponent and the Permit Holder of Agreement
No. CE 59/2005 (EP) Development of a Bathing Beach at Lung Mei, Tai Po (hereinafter
referred as ¡§the Project¡¨), which is a Designated Project to be implemented
under Environmental Permit number EP-388/2010 (hereinafter
referred as ¡§the EP-388/2010¡¨ or ¡§the EP¡¨).
ES.02 Action-United Environmental Services & Consulting (hereinafter referred as ¡§AUES¡¨) has been commissioned as the
Environmental Team for the Project (hereinafter referred as ¡§the ET¡¨) to
perform relevant Environmental Monitoring and Audit (EM&A) programme, including baseline and impact environmental
monitoring in accordance with the EM&A Manual approved under the Environmental
Impact Assessment Ordinance (EIAO).
ES.03 According to the Approved EM&A Manual
[November 2007] (hereinafter referred as ¡¥the EM&A Manual¡¦), air quality,
construction noise and water quality monitoring should be required to be
monitored for baseline and during the construction phase of the Project. In January 2018, an updated EM&A Manual (AUES Ref.: TCS00874/16/300/L0085 dated 11
January 2018) was prepared to update of noise and air sensitive receivers and recent site condition
for the EM&A programme and it was submitted and
approved by EPD in January 2018.
ES.04 This is the 35th
monthly EM&A report presenting the monitoring results and inspection
findings for the reporting period from 1st to 31st October 2020 (hereinafter ¡¥the Reporting Period¡¦).
In the Reporting Period, the impact monitoring covered air quality and
construction noise and post-project monitoring for marine water quality.
Environmental Monitoring and Audit Activities
ES.05 As advised by the Contractor and confirmed by
CEDD, all marine dredging was completed in late October 2019 and all sand laying underwater
has been substantially completed in late August 2020. It is confirmed that no further marine filling operation in the site after sub-tidal
profile survey check conducted on 31 August 2020 and CEDD have no adverse
comment on it. In view of completion
of all the marine activities including dredging and sand laying underwater, the
impact marine water quality monitoring for the
Project was terminated on 31 August 2020 according to the updated EM&A Manual Section 5.1.5. The notification of termination of
impact marine water quality monitoring was issued to CEDD, IEC and EPD without
adverse comment received.
ES.06 Pursuant to updated EM&A Manual Section 5.1.6, upon completion of sandfilling work, post-project marine water quality
monitoring would be conducted for 4 weeks in the same manner as the baseline monitoring, which scheduled to conduct in September
2020 and October 2020. Overall, most of
the monitoring result obtained during post project marine water monitoring are fall within and similar to the baseline data. It is considered that no adverse impact was caused to the marine water
quality after completion of the marine based construction works.
ES.07
Environmental
monitoring activities under the EM&A programme in the Reporting Period are summarized in the following
table.
Issues |
Environmental Monitoring Parameters /
Inspection |
Sessions Note 1 |
Air Quality |
1-hour
TSP |
6 |
24-hour TSP |
5 |
|
Construction
Noise |
LAeq(30min)
Daytime |
4 |
Water Quality |
Marine Water
Sampling |
(#) 12 |
Inspection / Audit |
ET Regular Environmental Site Inspection |
2 |
Independent
Environmental Checker (IEC) Monthly Environmental Site Audit |
1 |
Note: Impact
Marine water quality monitoring was completed on 31 August 2020. There were 12
session of post-project marine water quality monitoring conducted in the
Reporting Period.
Breach of Action
and Limit (A/L) Levels
ES.08
No
exceedance of air quality and construction noise monitoring were recorded in
this Reporting Period. The
statistics of environmental exceedance, NOE issued and investigation of
exceedance are summarized in the following table.
Environmental Issues |
Monitoring Parameters |
Exceedance |
Event &
Action |
||
Action Level |
Limit Level |
Investigation |
Corrective Actions |
||
Air Quality |
1-hour
TSP |
0 |
0 |
- |
- |
24-hour TSP |
0 |
0 |
- |
- |
|
Construction
Noise |
LAeq(30min) |
0 |
0 |
- |
- |
Environmental Complaint
ES.09 No environmental
complaint was recorded or received in this Reporting Period. The statistics of environmental
complaint are summarized in the following table.
Reporting Period |
Environmental Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
1 ¡V 31 October 2020 |
0 |
2 |
Dust (2) |
Notification of
Summons and Successful Prosecutions
ES.10
No
environmental summons or successful prosecutions were recorded in this
Reporting Period. The statistics of
environmental complaint are summarized in the following tables.
Reporting Period |
Environmental Summons Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
1 ¡V 31 October 2020 |
0 |
0 |
N/A |
Reporting Period |
Environmental Prosecution Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
1 ¡V 31 October 2020 |
0 |
0 |
N/A |
ES.11
There was no reporting
change in the EM&A programme
in
this Reporting Period.
ES.12 In the Reporting Period, joint
site inspection by ET and the Contractor was performed on 15th and 30th
October 2020. No
non-compliance was noted during the two occasions.
ES.13
The construction activities in November 2020 is road widening, sand
profile formation (land based), E&M Works and Landscaping. The potential environmental impacts arising from
the forthcoming
construction activities include construction
waste, air quality and construction noise.
ES.14
During the dry season, the dust mitigation
measures should be fully implemented such as water spraying during dust
work to minimize dust impact as appropriate. All dump trucks leaving the Site should be
thoroughly washed by wheel washing facilities and provided with mechanical covers
in good service condition.
ES.15
Construction noise should be a key environmental impact during the
works. Noise mitigation measures such
as use of quiet plants and installation of temporary noise barrier at the
construction noise predominate area should be fully implemented in accordance with the EM&A
requirement.
Table of Contents
2. Project Organization
and Construction Progress
2.1 Project
Organization and Management Structure
2.3 Summary of Environmental Submissions
3. Summary of Impact
Monitoring Requirements
3.4 Monitoring
Frequency and Period
3.7 Meteorological
Information
3.8 Determination
of Action/Limit (A/L) Levels
3.9 Data Management and Data QA/QC Control
4.2 Results
of Air Quality Monitoring
5. Construction Noise
Monitoring
5.2 Results
of Noise Monitoring
7.2 Records
of Waste Quantities
8.1 Ecology Monitoring (marine-based)
9.2 Findings
/ Deficiencies During the
Reporting Month
10. Environmental Complaint and
Non-Compliance
10.1 Environmental
Complaint, Summons and Prosecution
11. Implementation Status of
Mitigation Measures
12. Conclusions and Recommentations
List of TABLES
Table 2-1 Status
of Environmental Licenses and Permits
Table 2-2 Submission
Status as under the EP Stipulation
Table 3-1 Summary
of EM&A Impact Monitoring Requirements
Table 3-2 Location
of Air Quality Monitoring
Table 3-3 Designated
Noise Monitoring Station according to the EM&A Manual
Table 3-4 Noise
Monitoring Stations of the EM&A Programme
Table 3-5 Location
of Marine Water Quality Monitoring Station
Table 3-6 Air
Quality Monitoring Equipment
Table 3-7 Construction
Noise Monitoring Equipment
Table 3-8 Instrument
of Water Quality Monitoring
Table 3-9 Testing
Method and Reporting Limit of the Chemical Analysis
Table 3-10 Action and Limit
Levels for Air Quality
Table 3-11 Action and Limit
Levels for Construction Noise
Table 3-12 Action and Limit
Levels for Water Quality
Table 4-1 Summary
of 24-hour and 1-hour TSP Monitoring Results (A4)
Table 4-2 Summary
of 24-hour and 1-hour TSP Monitoring Results (A7)
Table 5-1 Construction
Noise Monitoring Results of N1
Table 5-2 Construction
Noise Monitoring Results of N2a
Table 5-3 Construction
Noise Monitoring Results of N3a
Table 5-4 Construction
Noise Monitoring Results of N4
Table 6-1 Results
Summary of Depth Average (Surface & Middle Layer) of DO (mg/L)
Table 6-2 Results
Summary of Bottom Depth of DO (mg/L)
Table 6-3 Results
Summary of Depth Average of Turbidity (NTU)
Table 6-4 Results
Summary of Depth Average of Suspended Solids (mg/L)
Table 6-5 Results
Summary of Depth Average of Chlorophyll-a (µg/L)
Table 6-6 Fluctuation
Ranges for the Monitored Post-Project Marine Water Quality Parameters
Table 7-1 Summary
of Quantities of Inert C&D Materials
Table 7-2 Summary
of Quantities of C&D Wastes
Table 8-1 Summary
of Submission for Seahorse Monitoring
Table 8-2 Summary
of Submission for Marine Ecological Monitoring
Table 9-1 Site
Observations
Table 10-1 Statistical
Summary of Environmental Complaints
Table 10-2 Statistical
Summary of Environmental Summons
Table 10-3 Statistical
Summary of Environmental Prosecution
Table 11-1 Environmental
Mitigation Measures in the Reporting Month
List
of Appendices
Appendix A Layout Plan of the Project
Appendix B Organization structure and
contact details
Appendix C 3-month rolling construction
program
Appendix D Monitoring Location
Appendix E Calibration Certificate of
Monitoring Equipment
Appendix F Event and Action Plan
Appendix G Impact Monitoring Schedules
Appendix H database of Monitoring Result
Appendix I Graphical plots of
Monitoring Results
Appendix J Meteorological Data
Appendix K Waste Flow Table
Appendix L Implementation Schedule of
Environmental Mitigation Measures
1.1.1
Civil Engineering
and Development Department (hereafter referred as ¡§CEDD¡¨) is the Project
Proponent and the Permit Holder of Agreement No. CE 59/2005 (EP)
Development of a Bathing Beach at Lung Mei, Tai Po (hereinafter
referred as ¡§the Project¡¨), which is a Designated Project to be implemented
under Environmental Permit number EP-388/2010 (hereinafter
referred as ¡§the EP-388/2010¡¨ or ¡§the EP¡¨).
1.1.2
The major construction activities of the
Project comprise construction of 200-metre
long bathing beach with a groyne at each end, a shark prevention net; a public car park;
retaining walls; and the associated roadworks, drainage and sewerage works. Layout plan of the Project is shown in Appendix A. Designated
works of the Project under the EP
shall include:
(i)
Construction of a 200m long beach with a groyne at each end of the beach which includes dredging and
sandfilling works;
(ii)
Construction of one culvert at the eastern side of the
beach and another small section of culvert and open drainage channel with
gabion embankments at the western end, both to collect and divert surface
runoff from upstream locations; and
(iii)
Construction of a beach building with associated beach
building facilities, kiosk and a carpark and associated road improvement works
adjoining the facility.
1.1.3
CEDD is Site
Resident Engineers (hereinafter referred as ¡§SRE¡¨) responsible for the Project
management; Welcome Construction CO., Ltd is a Main Contractor (hereinafter
referred as ¡§Contractor¡¨) responsible for construction
of the Project; and Action-United Environmental Services &
Consulting (hereinafter referred as
¡§AUES¡¨) has been commissioned as an Independent Environmental Team (hereinafter
referred as ¡§the ET¡¨) to implement the relevant EM&A programme in accordance with the approved EM&A
Manual, as well as the associated duties.
Moreover, Environmental Resources Management is Independent
Environmental Checker (hereinafter
referred as ¡§IEC¡¨) of the
Project.
1.1.4
As part of the Environmental Monitoring and
Audit (EM&A) programme, baseline monitoring to
determine the ambient environmental conditions including air quality, noise and
water quality were undertaken between 7 June 2017 and 21 October 2017. After completed baseline monitoring, Baseline Monitoring Report for Air Quality and Noise (AUES Ref.: TCS00874/16/600/R0022v3) and Baseline
Monitoring Report for
Water Quality (AUES Ref.:
TCS00874/16/600/R0036v2) were
verified by IEC and submitted to EPD for endorsement. These Baseline
Monitoring Reports have summarized the key findings of
baseline condition and
determined a set
of Action and Limit Levels (A/L Levels) based on the baseline
data. The A/L Levels will serve as the
yardsticks for assessing the acceptability of the environmental impact during
construction phase of the Project Works impact monitoring.
1.1.5
The construction phase of the Project commenced on
1st December 2017. Accordingly, the impact monitoring of the
EM&A programme commenced on the same date.
1.1.6
As advised by the Contractor and confirmed by CEDD, all marine dredging
was completed in late October 2019 and all sand laying underwater has been substantially completed in late August
2020. It is confirmed that no further marine filling operation in the site after
sub-tidal profile survey check conducted on 31 August 2020 and CEDD have no
adverse comment on
it. In view of completion of
all the marine activities including dredging and sand laying underwater, the impact marine water quality monitoring for the
Project was terminated on 31 August 2020 according to the updated EM&A Manual Section 5.1.5. The notification of termination of
impact marine water quality monitoring was issued to CEDD, IEC and EPD without
adverse comment received.
1.1.7
This is the 35th monthly EM&A report presenting the monitoring results and inspection
findings for the reporting period from 1st to 31st October 2020.
1.2.1
The Monthly EM&A Report is structured
into the following sections:-
Section 1 Introduction
Section 2 Project
Organization and Construction progress
Section 3 Summary of
Impact Monitoring Requirements
Section 4 Air
Quality Monitoring
Section 5 Construction
Noise Monitoring
Section 6 Water
Quality Monitoring
Section 7 Waste
Management
Section 8 Ecology
Section 9 Site
Inspection
Section 10 Environmental
Complaint and non-compliance
Section 11 Implementation
Status of Mitigation Measures
Section 12 Conclusion
and Recommendation
2.1.1
Organization structure and contact details of relevant parties
with respect to on-site environmental management are shown in Appendix B.
The responsibilities of respective parties are:
Engineer or Engineers
Representative (ER)
2.1.2
The ER is responsible for overseeing the construction works and
for ensuring that the works are undertaken by the Contractor in accordance with
the specification and contract requirements. The duties and responsibilities of
the ER with respect to EM&A are:
¡P
monitor the Contractor¡¦s compliance with contract specifications,
including the effective implementation and operation of environmental
mitigation measures and other aspects of the EM&A programme;
¡P
instruct the Contractor to follow the agreed protocols or those in
the Contract Specifications in the event of exceedances or complaints;
¡P
comply with the agreed Event and Action Plans in the event of any
exceedance;
¡P
liaise with the IEC and assist as necessary in the implementation
of the EM&A program; and
¡P
participate in joint site inspection undertaken by
the ET and IEC.
The Contractor
2.1.3
The duties and responsibilities of the Contractor are:
¡P
work within the scope of the construction contract and other
tender conditions;
¡P
provide assistance to the ET in carrying out monitoring;
¡P
Submit proposals on mitigation measures in
case of exceedances of Action and Limit levels in accordance with the Event and
Action Plans;
¡P
implement measures to reduce impact where Action and Limit levels
are exceeded;
¡P
implement the corrective actions instructed by ER/ET/IEC;
¡P
participate in the site inspections undertaken by the ET and the
IEC, as required, and undertake any corrective actions instructed by ER/ET/IEC;
and
¡P
adhere to the procedures for carrying out
complaint investigation.
Environmental Team (ET)
2.1.4
The ET will be led and managed by the ET Leader. The ET leader will have relevant
education, training, knowledge, experience and professional qualifications and
the appointment will be subject to the approval of the Director of
Environmental Protection and ER.
Suitably qualified staff will be included in the ET, and the ET should
not be in any way an associated body of the Contractor or the Independent
Environmental Checker (IEC) for the Project.
2.1.5
The duties and responsibilities of the ET are:
¡P
monitor various environmental parameters as required in this EM&A
Manual;
¡P
assess the EM&A data and review the success of the EM&A programme determining the adequacy of the mitigation
measures implemented and the validity of the EIA predictions as well as
identify any adverse environmental impacts before they arise;
¡P
carry out regular site inspection to investigate and audit the
Contractor¡¦s site practice, equipment and work methodologies with respect to
pollution control and environmental mitigation, and effect proactive action to
pre-empt issues;
¡P
review the Contractor¡¦s working programme
and methodology, and comment as necessary;
¡P
review and prepare reports on the environmental monitoring data,
site environmental conditions and audits;
¡P
report on the environmental monitoring and audit results and
conditions to the IEC, Contractor, EPD and ER;
¡P
recommend suitable mitigation measures to the Contractor in the
case of exceedance of Action and Limit levels in accordance with the Event and
Action Plans;
¡P
adhere to the procedures for carrying out complaint investigation;
and,
¡P
the ET Leader will keep a contemporaneous
log-book and record each and every instance or circumstance or change of
circumstances which may affect the environmental impact assessment and every
non-conformance with the recommendations of the EIA Reports or the EPs.
Independent Environmental Checker (IEC)
2.1.6
The duties and responsibilities of the IEC are:
¡P
review and monitor the implementation of the EM&A programme and the overall level of environmental
performance being achieved;
¡P
arrange and conduct monthly independent site inspections/audits of
the works;
¡P
validate and confirm the accuracy of monitoring results,
monitoring equipment, monitoring stations, monitoring procedures and locations
of sensitive receivers;
¡P
carry out random sample check and audit on monitoring data and
sampling procedures, etc;
¡P
audit the EIA recommendations and requirements against the status
of implementation of environmental protection measures on site;
¡P
on needed basis, audit the Contractor¡¦s construction methodology
and agree the appropriate, reduced impact alternative in consultation with ER,
the ET and the Contractor;
¡P
provide specialist advice to ER and the Contractor on
environmental matters;
¡P
check complaint cases and the effectiveness of corrective measures;
¡P
check that the necessary mitigation measures recommended in the
EIA, EP and Contract documents, or as subsequently required, are effectively
implemented;
¡P
review EM&A report submitted by the ET leader and feedback
audit results to ET by signing off relevant EM&A proformas;
¡P
report the findings of site inspections/ audits and other
environmental performance reviews to ER, ET, EPD and the Contractor;
2.2.1
The 3-month rolling construction program is enclosed in Appendix C and the major construction
activities undertaken in the Reporting Period are listed below:-
¡P
Road widening;
¡P
Structure above groyne;
¡P
Sand laying (land based);
¡P
Sand profile formation (land based);
¡P
E&M
works;
¡P
Lookout
Towers: and
¡P
Landscaping
2.3.1
Summary of currently relevant permits,
licenses, and/or notifications on environmental protection for this Project in
this Reporting Period is presented in Table 2-1.
Table 2-1 Status of Environmental Licenses and Permits
Item |
Description |
License/Permit Status |
||
Permit
no./Account no./ Ref. no. |
From |
To |
||
1 |
Air pollution Control (Construction
Dust) Regulation |
Ref. Number:
418137 |
N/A |
N/A |
2 |
Chemical Waste Producer Registration |
Waste
Producers Number (WPN): 5213-728-W3437-01 |
21 August
2017 |
End of
Project |
3 |
Water Pollution Control Ordinance |
License No.:
WT00028905-2017 |
24 October
2017 |
31 October
2022 |
4 |
Waste Disposal (Charges for Disposal of
Construction Waste) Regulation |
Billing
Account for Disposal of Construction Waste: Account No. 7017686 |
3 July 2013 |
End of
Project |
2.3.2
The submission status as under the EP
requirement is
presented in Table 2-2.
Table 2-2 Submission Status as under the EP Stipulation
Item |
EP
condition |
Description |
Status |
1 |
2.3 |
Management Organization of the Main Construction Companies |
The updated version was submitted in May 2018 |
2 |
2.4 |
Report for Capture and
Relocation of Common Rat
Snake |
Approved by EPD on 15 Sep 2017 (EPD ref.: (15) in
EP2/N5/C/46 Pt.6 dated 15 Sep 2017) |
3 |
2.5 |
Landscape Plan |
Submitted to EPD on 28 June 2017 |
4 |
3.12 |
Mangrove Seedling Planting Proposal |
Not yet submitted |
5 |
3.13 |
Detailed Landscape As-built
Drawing(s) |
Not yet submitted |
6 |
4.3 |
Baseline Monitoring Report for Air Quality
and Noise (AUES Ref.: TCS00874/16/600/R0022v3) |
Approved by EPD on 8 Jan 2018 (EPD ref.: (36) in
EP2/N5/C/46 Pt.6 dated 8 Jan 2018) |
7 |
Baseline Monitoring Report for Water
Quality(AUES Ref.:
TCS00874/16/600/R0036v2) |
Approved by EPD on 10 Jan 2018 (EPD ref.: (37) in
EP2/N5/C/46 Pt.6 dated 10 Jan 2018) |
3.1.1
The Environmental Monitoring and Audit requirements are set out in
the EM&A manual. Environmental issues such as air quality, construction
noise and water quality were identified as the key issues during the
construction phase of the Project.
A summary of the EM&A requirements for air quality, noise monitoring
and water quality are presented in the sub-sections below.
3.2.1
According to the Project EM&A Manual, the Impact monitoring programme
covers the following environmental issues:
Air Quality;
Construction Noise; and
Water Quality
3.2.2
A summary of the monitoring parameters is presented in Table
3-1 below.
Table 3-1 Summary
of EM&A Impact Monitoring Requirements
Environmental
Issue |
Parameters |
Air Quality |
1-hour TSP 24-hour TSP |
Noise |
Leq (30min) in six consecutive Leq(5 min) between 07:00-19:00 on normal
weekdays |
Water Quality |
In-situ Measurements Dissolved Oxygen
Concentration (mg/L); Dissolved Oxygen Saturation
(% ); Salinity (mg/L); Temperature (¢J); Turbidity (NTU); pH unit; Current direction (degree); Current speed (m/s); and Water depth (m) Laboratory Analysis Suspended Solids (mg/L); and Chlorophyll-a (µg/L) |
Air Quality
3.3.1
There are air quality monitoring locations (A4
and A6) recommended
in Section 3.1 of the EM&A Manual.
During liaison with the landlord of A6, he refused to provide access and
location for
installation of High Volume Air Sampler (HVAS). Therefore, alternative location (A7) was proposed by
ET in accordance with Section 3.4 of the EM&A Manual. The proposed alternative locations are considered capable
of effectively representing the baseline conditions at the impact monitoring
locations. The proposal (ref no.: TCS00874/16/300/L0016b) for alternative monitoring
locations was verified by IEC and it has been submitted to EPD for approval on 8 May 2017. The air quality
monitoring locations
are in Table
3-2 and illustrated in Appendix D.
Table 3-2 Location of Air Quality Monitoring
Station ID |
Location |
A4 |
No. 101 Lung Mei Tsuen |
A7 |
Hong Kong Eco-Farm |
Construction
Noise
3.3.2
According to Section 4.1 of the
EM&A Manual, four
designated noise sensitive receivers (N1, N2, N3 and N4) were
recommended and they are listed in Table 3-3 and illustrated in Appendix D.
Table 3-3 Designated
Noise Monitoring Station according to the EM&A Manual
NSR |
Location |
N1 |
Village
house - No. 165A Lung Mei |
N2* |
Village
house - No. 103 Lung Mei |
N3 |
Village
house - No. 70 Lo Tsz Tin |
N4 |
Village
house - No. 79 Lo Tsz Tin |
Remarks:
(*) Noise monitoring should be conducted at N2a (i.e House No. 101 Lung Mei) if it is changed to residential
use during construction phase.
3.3.3
As confirmed on the first day of
baseline monitoring, N2a (House no. 101 Lung Mei) has been changed to
residential use. Therefore, the
noise monitoring is conducted at N2a and to replace N2. Moreover, due to the lack of accessibility of noise
monitoring at N3 (Village house ¡V No. 70 Lo Tsz Tin),
alternative location was proposed to replace N3 to carry out
the noise monitoring.
Having reviewed the surrounding condition, N3a (Village house ¡V No. 66C Lo Tsz Tin) was proposed with the rationales summarized in
below.
1)
The
distance between N3 and N3a is about 18 meter apart and N3a locates at close
proximity of the project site and major site activities which are likely to
have noise impacts;
2)
N3a is
a village type residential house and it is a noise sensitive receiver (NSR);
3)
Accessibility
for noise monitoring work at N3a is available; and
4)
Minimal
disturbance would be only caused to the proposed monitoring location N3a.
3.3.4
The proposal (ref no.:
TCS00874/16/300/L0016b) for alternative monitoring locations was
verified by IEC and it has been submitted to EPD for approval on 8 May 2017. The noise monitoring
stations under the EM&A programme are listed in Table 3-4 and illustrated in Appendix D.
Table 3-4 Noise Monitoring Stations of the EM&A Programme
Station ID |
Address |
N1 |
Village
house No. 165A of Lung Mei |
N2a |
Village
house No. 101 of Lung Mei |
N3a |
Village
house No. 66C of Lo Tsz Tin |
N4 |
Village
house No. 79 of Lo Tsz Tin |
Water Quality
3.3.5
According to Section 5.1.2 of the Approved EM&A Manual, two Reference Stations
(R1 and R2), three impact stations (I1, I2 and I3), three sensitive receivers (FCZ1, W1 and M1) and one Gradient station (G1),
were identified
to perform water quality monitoring.
Detailed and coordinates of water quality monitoring stations is
described in Table 3-5 and the graphical is shown in Appendix D.
Table 3-5 Location
of Marine Water Quality Monitoring Station
Station |
Coordinates |
Description |
|
Easting |
Northing |
||
G1 |
841483.9 |
835936.1 |
Gradient Station - to assist in the identification of the
source of any impact. |
R1 |
842307.4 |
835718.4 |
Reference Station - for the background water quality for Tolo Harbour as it is at the
channel where the water exchange between the enclosed Plover Cove and Tolo Harbour take place. It is
located at south of the Project dredging/sandfilling
area. |
R2 |
840739.4 |
836212.4 |
Reference Station - for the background water quality in the Plover
Cove region. It is located at
southwest of the Project dredging/sandfilling area. |
I1 |
841338.5 |
836588.5 |
Impact Station - located outside the mixing zone of
dredging/sandfilling works of the Project. |
I2 |
841590.3 |
836601.2 |
Impact Station - located outside the mixing zone of
dredging/sandfilling works of the Project. |
I3 |
841807.0 |
836680.9 |
Impact Station - located outside the mixing zone of
dredging/sandfilling works of the Project. |
W1 |
841858.9 |
836571.0 |
Sensitive Receiver - located at the Water Sport Centre,
which is about 0.25 km distance to the southeast of the dredging/sandfilling area. |
M1 |
840822.2 |
836416.4 |
Sensitive Receiver - located at the Ting Kok
SSSI, which is about 0.8 km distance to the west of the dredging/sandfilling area. |
FCZ1 |
841180.6 |
835230.8 |
Sensitive Receiver - located at the Yim Tin Tsai East Fish
Culture Zone, which is about 1.5 km distance to the southwest of the
dredging/sandfilling area. |
3.4.1
The frequency and the
duration for impact monitoring are summarized below.
Air Quality Monitoring
Parameters: |
1-hour TSP and 24-hour TSP |
Frequency: |
3 times every six
days for 1-hour TSP and once every 6 days for 24-hour TSP |
Duration: |
Throughout the
construction period |
Noise Monitoring
Parameters: |
LAeq(30min) and statistical results L10 & L90 |
Frequency: |
Leq (30min) in 6
consecutive Leq(5min) for once a week during
07:00-19:00 on normal weekdays |
Duration: |
Throughout the
construction period |
Water Quality (Marine) Monitoring
Parameters: |
In-situ measurements including water
depth, Dissolved
Oxygen (DO) concentration (mg/L) & saturation (%), Salinity (mg/L),
Temperature (ºC) and Turbidity (NTU); and Suspended Solids (mg/L) and Chlorophyll-a (µg/L) are analyzed by
HOKLAS-accredited laboratory. |
Frequency: |
Three days a week, at mid ebb and mid
flood tides. The interval between 2 sets of monitoring
will be more than 36 hours. |
Sampling Depth |
1)
Three depths: 1m below water surface, 1m
above sea bottom and at mid-depth when the water depth exceeds 6m; 2)
If the water depth is between 3m and 6m,
two depths: 1m below water surface and 1m above sea bottom; and 3)
If the water depth is less than 3m, 1
sample at mid-depth is taken |
Duration: |
During marine works proceeding such as the dredging and sand filling |
3.4.2
In addition to the water quality
parameters, other relevant data will also be to measure and record, which are
included the location of the sampling stations, water depth, time, weather
conditions, sea conditions, tidal stage, current water flow direction and
speed, special phenomena and work activities undertaken around the monitoring
and works area that may influence the monitoring results. Observations on any special phenomena
and work underway at the Project site during the time of sampling will also be
to record.
Air Quality Monitoring
3.5.1
The 24-hour and 1-hour TSP levels shall be measured by following
the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B. If the ET proposes to use a direct
reading dust meter to measure 1-hour TSP levels, it shall submit sufficient information
to the IEC to prove that the instrument is capable of
achieving a comparable results to the HVS.
The instrument should be calibrated regularly, and the 1-hour sampling
shall be determined on yearly basis by the HVS to check the validity and accuracy
of the results measured by direct reading method. The filter paper of 24-hour TSP measurement shall be determined by HOKLAS
accredited laboratory.
3.5.2
All equipment to be used for air quality monitoring is listed in Table
3-6.
Table 3-6 Air
Quality Monitoring Equipment
Equipment |
Model |
24-Hour TSP |
|
High Volume Air Sampler |
TISCH High Volume Air Sampler, HVS Model
TE-5170 |
Calibration Kit |
TISCH Calibration Kit Mode TE-5025A |
1-Hour TSP |
|
Portable Dust Meter |
Sibata LD-3B Laser Dust Meter |
Noise Monitoring
3.5.3
Sound level meter in
compliance with the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1)
specifications shall be used for carrying out the noise monitoring. The sound level meter shall be checked
using an acoustic calibrator. The
wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in ms-1 for reference.
3.5.4
Monitoring equipment to be used for construction noise measurement
is listed in Table 3-7.
Table 3-7 Construction
Noise Monitoring Equipment
Equipment |
Model |
Integrating Sound Level Meter |
Rion NL-52 |
Acoustic Calibrator |
Rion NC-73 |
Portable Wind Speed Indicator (#) |
Anemometer
AZ Instrument 8908 |
(#) Wind speed is reference data only and there is
no calibration certificate for portable wind speed indicator.
Water Quality Monitoring
3.5.5
For
water quality monitoring, the used equipment should be fulfill the requirements
under the Approved EM&A
Manual Section 5.1.1. Requirement of instruments is described in
the following sections.
3.5.6
Instruments to be used for
Water quality monitoring is listed in Table 3-8.
Table 3-8 Instrument
of Water Quality Monitoring
Equipment |
Model |
A Digital Global Positioning
System |
Garmin eTrex
|
Water Depth Detector |
Garmin ECHO 100 |
Water Sampler |
Aquatic
Research Transparent PC
Vertical Water Sampler 2.2L
/ 3L / 5L |
Thermometer & DO meter |
YSI
EXO-3 Multi-parameter Water Quality Meter |
pH meter |
|
Turbidimeter |
|
Salinometer |
|
Current Meter |
Valeport Current Meter 106CM |
Storage Container |
¡¥Willow¡¦ 33-litre plastic cool box with Ice
pad |
3.5.7
The following equipment and facilities shall be
provided and used for the monitoring of water quality impacts:
Dissolved Oxygen and Temperature Measuring Equipment
3.5.8
DO and water temperature shall be measured in-situ
by a DO/ temperature meter. The instrument shall be portable and weatherproof
using a DC power source. It shall have a membrane electrode or an optical
dissolved oxygen sensor with automatic temperature compensation complete with a
cable. The equipment shall be capable of measuring:
DO level in the range of 0-20 mg/l and 0-200% saturation; and
Temperature of between 0 and 45 degree Celsius with a capability
of measuring ¡Ó 0.1 degree Celsius.
Turbidity Measurement Instrument
3.5.9
The instrument shall be portable and weatherproof
using a DC power source. It shall have a photoelectric sensor capable of
measuring turbidity between 0-1000 NTU.
Salinity
3.5.10
A portable salinometer
with measuring range of 0-40 mg/l shall be used to determine the salinity of
the water.
Water Depth Detector
3.5.11
A portable, battery-operated echo sounder shall be
used for the measurement of water depth at each designated monitoring station.
The unit shall be either handheld or affixed to the bottom of the work boat, if
the same vessel is to be used throughout the monitoring programme.
Positioning Device
3.5.12
A hand-held or boat-fixed type digital Global
Positioning System (dGPS) with way point bearing
indication or other equivalent instrument of similarly accuracy should be
provided and used during monitoring to ensure the monitoring vessel is at the
correct location before taking measurements.
Water Sampling Equipment
3.5.13
A water sampler comprises a transparent PVC
cylinder, with a capacity of not less than 2 litres,
and could be effectively sealed with latex cups at both ends shall be used. The
sampler has a positive latching system to keep it open and prevent premature
closure until it is released by a messenger when the sampler is at the
predetermined water depth (Kahlsico Water Sampler or
other approved instrument).
3.5.14
Water samples shall be collected in high density
polythene bottles, packed in ice (cooled to 4¢XC without being
frozen), and delivered to the laboratory within 24 hours possible after
collection. Each bottle will be labelled on the surface with date, location,
tide, parameter and replicate information of the sample.
Air Quality
1-hour TSP
3.6.1
Operation of the 1-hour TSP meter will follow manufacturer¡¦s Operation and Service Manual.
3.6.2
The 1-hour TSP monitor, brand named ¡§Sibata LD-3B Laser Dust Meter¡¨ is a portable, battery-operated laser photometer.
The 1-hour TSP meter provides a real time 1-hour TSP measurement based on 900
light scattering. The 1-hour TSP monitor consists of the following:
a.
A pump
to draw sample aerosol through the optic chamber where TSP is measured;
b.
A
sheath air system to isolate the aerosol in the chamber to keep the optics
clean for maximum reliability; and
c.
A
built-in data logger compatible with Windows based program to facilitate data
collection, analysis and reporting.
3.6.3
The 1-hour
TSP meter to be used will be within the valid period, calibrated by the manufacturer
prior to purchasing. Zero response of the instrument will be checked before and after each monitoring event. Annually calibration with the High
Volume Sampler (HVS) in same condition would be undertaken by the Laboratory.
24-hour TSP
3.6.4
The equipment used for 24-hour TSP measurement is the High
Volume Sampler (hereinafter the ¡§HVS¡¨) brand named TISCH, Model TE-5170 TSP
High Volume Air Sampler, which complied with EPA Code of Federal Regulation, Appendix B to Part 50. The HVS consists of the following:
a.
An anodized aluminum shelter;
b.
A 8¡¨x10¡¨ stainless steel filter holder;
c.
A blower motor assembly;
d.
A continuous flow/pressure recorder;
e.
A motor speed-voltage control/elapsed time indicator;
f.
A 7-day mechanical timer, and
g.
A power supply of 220v/50 hz
3.6.5
For HVS for 24-hour TSP monitoring, the HVS is mounted in a
metallic cage with a top for protection and also it is sat on the existing
ground or the roof of building. The
flow rate of the HVS between 0.6m3/min and 1.7m3/min will
be properly set in accordance with the manufacturer¡¦s instruction to within the
range recommended in EPA Code of Federal
Regulation, Appendix B to Part 50. Glass Fiber Filter 8" x 10" of
TE-653 will be used for 24-Hour TSP monitoring and would be supplied by
laboratory. The general procedures
of sampling are described as below:-
A horizontal platform with appropriate support to secure the
samples against gusty wind should be provided;
No two samplers should be placed less than 2 meters apart;
The distance between the sampler and an obstacle, such as
building, must be at least twice the height that the obstacle protrudes above
the sample;
A minimum of 2 meters of separation from any supporting structure,
measured horizontally is required;
Before placing any filter media at the HVS, the power supply will
be checked to ensure the sampler work properly;
The filter paper will be set to align on the screen of HVS to
ensure that the gasket formed an air tight seal on the outer edges of the
filter. Then filter holder frame
will be tightened to the filter hold with swing bolts. The holding pressure should be sufficient
to avoid air leakage at the edge.
The mechanical timer will be set for a sampling period of 24 hours
(00:00 mid-night to 00:00 mid-night next day). Information will be recorded on the
field data sheet, which would be included the sampling data, starting time, the
weather condition at current and the filter paper ID with the initial weight;
After sampling, the filter paper will be collected and transfer
from the filter holder of the HVS to a sealed envelope and sent to a local
HOKLAS accredited laboratory for quantifying.
3.6.6
All the sampled 24-hour TSP filters will be
collected and put into the filter envelope provided by the laboratory. The sample will be kept in normal air conditioned
room conditions, i.e. 70% HR (Relative Humidity) and 25oC and
delivery to the office within 48 hours and sent to laboratory for
analysis. The sampled filter will
be kept in the laboratory for six months prior to disposal.
3.6.7
The HVS used for 24-hour TSP monitoring will be calibrated before
the commencement for sampling, and after in two months interval for 1 point
checking of maintenance and six months interval for five points calibrate in
accordance with the manufacturer¡¦s instruction using the NIST-certified
standard calibrator (TISCH Calibration Kit Model TE-5025A) to establish a relationship
between the follow recorder meter reading in cfm (cubic feet per minute) and
the standard flow rate, Qstd, in m3/min. Motor brushes of HVS will be regularly
replaced of about five hundred hours per time.
Construction Noise
3.6.8
As referred to in the Technical Memorandum (TM) issued under the
NCO, sound level meters in compliance with the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804:1985 (Type 1) specifications
shall be used for carrying out the noise monitoring. Immediately prior to and
following each noise measurement the accuracy of the sound level meter shall be
checked using an acoustic calibrator generating a known sound pressure level at
a known frequency. Measurements may be accepted as valid only if the
calibration levels from before and after the noise measurement agree to within
1.0 dB.
3.6.9
All noise measurements will be performed with the meter set to
FAST response and on the A-weighted equivalent continuous sound pressure level (Leq). Leq(30 min) in six
consecutive Leq(5 min) measurements will be used as the
monitoring parameter for the time period between 07:00-19:00 hours on weekdays.
3.6.10
The sound level meter will be mounted on a tripod at a height of
1.2 m and placed at the assessment point and oriented such that the microphone
is pointed to the site with the microphone facing perpendicular to the line of
sight. The windshield will be fitted for all measurements. Where a
measurement is to be carried out at a building, the assessment point would
normally be at a position 1 m from the exterior of the building façade. Where a measurement
is to be made for noise being received at a place other than a building, the
assessment point would be at a position 1.2 m above the ground in a free-field
situation, i.e. at least 3.5 m away from reflective surfaces such as adjacent
buildings or walls.
3.6.11
Immediately prior to and following each noise measurement the
accuracy of the sound level meter will be checked using an acoustic calibrator
generating a known sound pressure level at a known frequency. Measurements will be accepted as valid
only if the calibration level from before and after the noise measurement
agrees to within 1.0 dB.
3.6.12
Noise measurements will not be made in fog, rain, wind with a
steady speed exceeding 5m/s or wind with gusts exceeding 10m/s. The wind speed
will be checked with a portable wind speed meter capable of measuring the wind
speed in m/s.
Water Quality (Marine) Monitoring
3.6.13
Marine water quality monitoring will be conducted at the
designated locations in accordance with EM&A Manual. The operating and
analytical of sampling procedures are described as below:
Water quality monitoring
locations shall be located by GPS prior to in-situ monitoring and sampling. Water depth
should be determined by using portable echo sounder for each monitoring location.
Measurements shall be taken at
3 water depths: 1m below water surface, mid-depth and 1m above sea bed, except
where the water depth less than 6m, the mid-depth station may be omitted.
Should the water depth be less than 3 m, only the mid-depth station will be
monitored.
Water samples should be
collected repeatedly using the water sampler as described in Section 3.5.13 to obtain adequate water
samples for laboratory analysis.
Sample container should be
pre-labeled with date, location, tide, parameter and
replicate information of the sample. The container should be rinsed using a
portion of the marine water sample before the container is filled. Container is
sealed with a screw cap after the filling is completed. The filled sample
containers are then packed in ice (cooled to 4¢XC without being frozen), and delivered to
the laboratory on the same day of collection for analysis.
Two consecutive in-situ
readings of water temperature, turbidity, dissolved oxygen, salinity, pH and
water depth should taken at a predetermined depth.
Where the difference in the value between the first and second readings of each
set is more than 25% of the value of the first reading, the reading is
discarded and further readings is taken.
3.6.14
All in-situ
monitoring instruments shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or any other international accreditation
scheme before use, and subsequently re-calibrated at 3 months intervals
throughout the water quality monitoring programme. Responses of sensors and
electrodes shall be checked with certified standard solutions before each use.
Certificate for calibration of in-situ instruments shall also be provided for
auditing.
3.6.15
Wet bulb
calibration for a DO probe shall be carried out at least once per monitoring
day. A zero check in distilled water shall be performed with the turbidity
probe at least once per monitoring day. The probe shall then be calibrated with
a solution of known NTU. In addition, the turbidity probe shall be calibrated
at least twice per month to establish the relationship between turbidity
readings (in NTU) and levels of suspended solids (in mg/L).
3.6.16
For the on-site
calibration of field equipment, the BS 1427: 1993, Guide to Field and On-Site
Test Methods for the Analysis of Waters should be observed. Sufficient stocks
of spare parts shall be maintained for replacements when necessary. Backup
monitoring equipment shall also be made available so that monitoring is
uninterrupted even when some equipment is under maintenance or calibration etc.
3.6.17
Before each
round of monitoring, the dissolved oxygen probe will be calibrated by wet bulb
method; a zero check in distilled water will be performed with the turbidity
and salinity probes; 4 and 10 values of the standard solution will be
undertaken to check the accuracy of pH value.
Laboratory Analysis
3.6.18
Sufficient
water samples shall be collected at the monitoring stations for carrying out
laboratory determination. Analysis of suspended solids and Chlorophyll-a should be carried out
in a HOKLAS or other international accredited laboratory. The
chemicals analysis method and reporting limit is shown Table 3-9.
Table 3-9 Testing Method and
Reporting Limit of the Chemical Analysis
Parameter |
ALS Method Code |
In-house
Method Reference 1 |
Reporting Limit |
Total
Suspended Solids |
EA025 |
APHA
2540D |
2 mg/L |
Chlorophyll-a |
EP008F |
APHA 10200H |
1 £gg/L |
Note: The exact method
shall depend on the laboratory accredited method. APHA
= Standard Methods for the Examination of Water and Wastewater by the American
Public Health Association.
3.6.19
Valid calibration
certificates of monitoring equipment of air quality, construction noise and
water quality are shown in Appendix E.
3.7.1
The meteorological information including wind direction, wind speed,
humidity, rainfall, air pressure and temperature etc. during impact
monitoring is
extracted from the closest Hong Kong Observatory Station. To obtain the most appropriate meteorological information
where available,
Air Temperature/Pressure and Relative Humidity will be extracted from Tai Po
Station and wind speed and direction will be extracted from Tai Mei Tuk Station.
3.8.1
The baseline results form the basis for determining the
environmental acceptance criteria for the impact monitoring. A summary of the Action/Limit (A/L)
Levels for air quality, construction noise and water quality are shown in Table
3-10, 3-11 and 3-12 respectively.
Table 3-10 Action
and Limit Levels for Air Quality
Monitoring Station |
Action Level (mg /m3) |
Limit Level (mg/m3) |
||
1-hour TSP |
24-hour TSP |
1-hour TSP |
24-hour TSP |
|
A4 |
275 |
142 |
500 |
260 |
A7 |
274 |
141 |
500 |
260 |
Table 3-11 Action and Limit Levels for
Construction Noise, dB(A)
Time Period: 0700-1900 hours on normal weekdays |
||
Monitoring Location |
Action Level |
Limit Level Note 1 & Note 2 |
N1,
N2a, N3a, and N4 |
When one documented complaint
is received |
75 |
Note 1: Acceptable Noise Levels for school should be
reduced to 70 dB(A) and65 dB(A) during examination period
Note 2: If works are to be carried out during
restricted hours, the conditions stipulated in the construction noise
permit issued by the NCA have to be followed.
Table 3-12 Action and Limit Levels for
Water Quality
Monitoring Location |
Action Level |
Limit Level |
||
Depth Average of SS (mg/L) |
||||
I1 |
7.0 |
OR
120% of any reference stations at the same tide of the same day |
7.5 |
OR
130% of any reference stations at the same tide of the same day |
I2 |
7.0 |
8.1 |
||
I3 |
8.3 |
15.0 |
||
W1 |
8.0 |
8.6 |
||
M1 |
10.0 |
11.0 |
||
FCZ1 |
7.0 |
8.0 |
||
Monitoring Location |
Dissolved
Oxygen (mg/L) |
|||
Depth
Average of Surface & Mid-depth |
Bottom |
Depth
Average of Surface & Mid-depth |
Bottom |
|
I1 |
5.08 |
N/A |
4.80 |
N/A |
I2 |
5.26 |
3.64 |
4.88 |
3.37 |
I3 |
5.03 |
4.09 |
4.77 |
3.19 |
W1 |
4.67 |
2.41 |
4.54 |
2.33 |
M1 |
4.73 |
N/A |
4.70 |
N/A |
FCZ1 |
5.00 |
3.43 |
5.00 |
3.18 |
Monitoring Location |
Depth Average
of Turbidity (NTU) |
|||
I1 |
2.8 |
OR
120% of any reference stations at the same tide of the same day |
2.9 |
OR 130% of any reference stations at the same tide
of the same day |
I2 |
3.5 |
7.7 |
||
I3 |
2.6 |
3.0 |
||
W1 |
2.9 |
3.3 |
||
M1 |
5.2 |
6.6 |
||
FCZ1 |
3.2 |
3.4 |
||
Monitoring Location |
Surface, Middle
& Bottom of
Chlorophyll-a (£gg/L) |
|||
I1 |
11.1 |
12.1 |
||
I2 |
11.0 |
13.1 |
||
I3 |
11.3 |
14.5 |
||
W1 |
11.3 |
16.1 |
||
M1 |
16.9 |
42.4 |
||
FCZ1 |
11.8 |
12.5 |
Notes:
(a)
For
DO, non-compliance of water quality limits occurs when monitoring result is
lower than the limits
(b)
For
SS, chlorophyll-a and turbidity, non-compliance of the
water quality limits occurs when monitoring result is higher than the limits.
(c)
Both
Action and Limit Levels for DO (surface and middle) in the FCZ1 are less than 5
mg/L.
3.8.2
Should
non-compliance of the environmental quality criteria occurs, remedial actions
will be triggered according to the Event and Action Plan which presented in Appendix F.
3.9.1
The impact monitoring data were handled by the
ET¡¦s in-house data
recording and management system.
3.9.2
The monitoring data recorded in the equipment were downloaded
directly from the equipment at the end of each monitoring day. The downloaded monitoring data were
input into a computerized database properly maintained by the ET. The laboratory results were input
directly into the computerized database and checked by personnel other than
those who input the data.
3.9.3
For monitoring parameters that require laboratory analysis, the
local laboratory shall follow the QA/QC requirements as set out under the
HOKLAS scheme for the relevant laboratory tests.
4.1.1
In the Reporting Period, air quality monitoring were
performed at the proposed monitoring
locations A4 and A7. The air quality monitoring schedule is
presented in Appendix G and the monitoring results are summarized in the following
sub-sections.
4.2.1
In the Reporting Period, 6 sessions of 1-hour TSP and 5 sessions 24-hour TSP were performed
at Stations A4 and A7. The
monitoring results for
air quality monitoring are summarized in Tables
4-1 to 4-2. The detailed 24-hour
TSP and 1-hour TSP monitoring data are presented in Appendix H and the relevant graphical plots are shown in Appendix I. The
meteorological data during the impact monitoring period are summarized in Appendix J.
Table 4-1 Summary
of 24-hour and 1-hour TSP Monitoring Results (A4)
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
6-Oct-20 |
49
|
3-Oct-20 |
9:54 |
71 |
74 |
66 |
12-Oct-20 |
40
|
7-Oct-20 |
9:18 |
66 |
73 |
72 |
17-Oct-20 |
52
|
15-Oct-20 |
9:24 |
70 |
71 |
68 |
23-Oct-20 |
53
|
19-Oct-20 |
9:20 |
74 |
70 |
65 |
29-Oct-20 |
35
|
24-Oct-20 |
9:50 |
70 |
72 |
68 |
|
30-Oct-20 |
13:09 |
78 |
74 |
70 |
|
Average (Range) |
46 (35 ¡V 53) |
Average (Range) |
71 (65 ¡V 78) |
Table 4-2 Summary
of 24-hour and 1-hour TSP Monitoring Results (A7)
Date |
24-hour TSP (mg/m3) |
1-hour TSP (mg/m3) |
||||
Date |
Start Time |
1st reading |
2nd reading |
3rd reading |
||
6-Oct-20 |
22
|
3-Oct-20 |
9:45 |
75 |
72
|
70
|
12-Oct-20 |
51
|
7-Oct-20 |
9:41 |
64 |
69
|
77
|
17-Oct-20 |
53
|
15-Oct-20 |
12:40 |
63 |
64
|
60
|
23-Oct-20 |
58
|
19-Oct-20 |
9:33 |
73 |
78
|
71
|
29-Oct-20 |
68
|
24-Oct-20 |
9:41 |
73 |
76
|
72
|
|
30-Oct-20 |
13:15 |
81 |
75
|
79
|
|
Average (Range) |
50 (22 ¡V 68) |
Average (Range) |
72 (60 ¡V81) |
4.2.2
As shown in Tables 4-1 to 4-2, all the 1-hour TSP and
24-hour TSP monitoring results were below
the Action / Limit Level. No
Notification of Exceedance (NOE) was issued in this Reporting Period.